April 30, 2010 |
|
This looks great! Until the weekend, we have laid the wall tiles in the bathrooms on 1st and 2nd floor. Next week they are going to be grouted.
Now in reality the harmony between wall and floor tiles. |
|
 |
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Plastering works in both sleeping rooms on 1st floor are finished. The rooms are spacious and light. |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
 |
|
|
|
|
|
After mounting all water supplies for the pool, the fundament for the back wall can be build. This wall will be also 2m high and faced with natural stones. |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The stairs have to be ready before we can lay the floor tiles.
Until the end of the week we finished the stairs to the 1st floor and Miguel
is beginning with the stairs to the
2nd floor.
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The armouring works at the pool are finished.
Jens is going to install the heating elements at the sides next week and then we can build the tank from sprayed concrete. |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Another part of the plastering works
on the outside are finished. The side walls of the terrace on 1st floor get their final rendering. |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
April 23, 2010 |
|
The base plate for the patio is cast,
all the supply drains for power and water are laid and the stair steps to the pergola and the garden are in preparation.
The stairs to the pergola will be as wide as the patio and in the back area we are going to install a fountain. |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Until the end of the week all tiles of
the first floor are laid and grouted.
Only the border areas of the stair steps are missing and can only be finished when the stair steps are set.
The plastering works on 2nd floor are almost finished and one can see now, how the rooms look like once they are ready. |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The armouring works of the pool are continuing. The floor drain is also prepared and Jens is setting the supply drains for the pool heating.
We sorted out something special:
The optimacasa pool is probably the first one on the whole island with a wall heating system! |
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
April 19, 2010 |
|
First thing on Monday morning we
will begin with the casting of the ground plate of the patio. Now, when everything is plain and even, one can see, how spacious the patio will be. |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
April 16, 2010 |
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The "tiling team" gets support and that makes tiling really faster.
The terraces of 1st and 2nd floor are ready laid and are now going to be grouted. On 2nd floor, most of the tiles are laid too and we start preparations for the tiling of the 1st floor. |
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
All electrical and sanitary installations in the outer area are laid and the big patio is arranged.
Beginning on Friday, the armouring irons are laid and the ground plate of the patio can be cast. |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
All supply pipes for the pool and the garden watering are set and the fundament for the ground plate of the patio is prepared.
Since there are so many pipes now (additional to the recirculation there is also the pool heating). We sorted out something special.
The optimacasa pool is the first one with a wall heating system! |
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The installation works in the pool area are continuing.
The skimmers and the pool illumination are set and the supply pipes for the recirculation are prepared.
Preparations of the machinery room are finished, so the floor can be tiled. |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
April 09, 2010 |
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
 |
The first room finished with skim will be the guest room
on ground floor. Skim is a breathing chalk product, bright white once it is dry and painting the walls is not necessary. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The small stairway to the basement of the garden is bricked and nowroughly plastered.
The huge patio is prepared continously, the surrounding fundaments are cast and the conduit for the feed pipes of the pool and for the electrical installations is prepared.
The correspondent conduits have to be laid in and prepared to have the concrete board to be cast. |
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The skimmers and the injectors for the pool have arrived and the correspondent black-outs can be chiseled out.
Once the positioning of the installations is made, we can begin with armouring works. |
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Both bath tubs are prepared for tiling. |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
First tiling works on the outer area take place on the big terrace of 2nd floor.
Before we can begin, we have to check the position of the first row of tiles, not to have ugly cuts.
In the centre of the terrace we install a relaxing gap and there is a decline to the two rain drainages.
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The upper terrace is finished, the flues are set and all walls are plastered.
On the apron the stand for the big satellite dish will be positioned. So there is no need to drill into the ground and the terrace will stay water proof. |
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|