Diary - March 2010       Navi   Navi
March 31, 2010 The week before Easter is short and only lasts until Wednesday. Nevertheless, we continued very well.

The side walls on the roof terrace are plastered, the fundament for the satellite installation is prepared and
we only have to plaster the two chimneys to finish the
roof terrace.
Image optimacasa
Image optimacasa
                     
  The border and the stairway to the basement within the garden area is ready armoured and bricked.

The ring anchor at the southern wall
of the patio is cast. We installed five tubes within the wall, to be used at a later stage for a framework for sun shades.
  Image optimacasa
                     
  Image optimacasa   Image optimacasa   Image optimacasa
                     
  Now all the window frames at the terrace on second floor are ready.

The window frames on first floor can only be fixed, when the floor plate of the patio is cast and a scaffolding
can be installed.
  Image optimacasa
                     
  Image optimacasa Image optimacasa
Image optimacasa
                     
  The tiled shower bowls get a safety painting and are sealed like the outer terraces.

Both bath tubs are set and for safety reasons filled with water.
  Image optimacasa   Image optimacasa
                     
  Image optimacasa Image optimacasa
                     
March 26, 2010 Week Review:

Storefronts:
The window frames of the storefront
of the 1st floor are ready and now the same type of work can begin on the garden direction.

The impermeability of the terraces
has been proven and as soon as
the delivery arrives, we will begin
with the tiling of the terrace.
  Image optimacasa
                     
  Image optimacasa Image optimacasa
                     
  Inner flooring:
The design for the laying of the floor tiles is set. The tiles will be laid parallel to the storefront, shifted on a third. We tried that in the living room and start with it now in the bodega.
  Image optimacasa
                     
  Image optimacasa   Image optimacasa   Image optimacasa
                     
  Inner rooms:
The basement rooms are nearly finished now. After the floor tiles are laid, José and Sevi can begin with skimming. After finishing these works, only missing things are the electrical installations.
  Image optimacasa
                     
  Image optimacasa Image optimacasa
                     
  Outer area:
The outer wall in the South of the
patio has reached its definite height and a ring anchor is prepared.
  Image optimacasa
                     
  Image optimacasa Image optimacasa
                     
  Stairs:
First treads have been set, the ones from the living room leading to the bodega. It looks great and I am looking forward to having the treads set in the stairway.
Image optimacasa
Image optimacasa
                     
  Image optimacasa   Image optimacasa
                     
  Swimming Pool:
The completion of the front of the pool is bricked,
the whole floor area is filled with gravel and we can
begin with the armouring works. But before we can
start with that, we have to set skimmer, lights and injectors. These parts should be delivered next week.
Image optimacasa
                     
March 19, 2010 Image optimacasa Image optimacasa
                     
  We continue very fast with the swimming pool. The surrounding
wall is nearly ready and the base
is filled with gravel.

The fundament for the surrounding wall of the estate behind the pool is preapared.

Next week, the pool will be closed
and the armouring works can begin.
  Image optimacasa
                     
  Image optimacasa Image optimacasa
                     
  On first floor all the inner window frames are prepared for the final rendering now.

Miguel is beginning to set the Mares stones on the outer window frames and the window sills on the upper floor are also placed.
  Image optimacasa
                     
March 18, 2010 The installations within the machinery room are proceeding fastly. Unbelievable, how many tubes have
to be laid, brazed and screwed. Jens is still having the overview and answers my questions with patience.

The last false ceiling in the basement is prepared and
we can start with the final rendering.
Image optimacasa
                     
  Image optimacasa   Image optimacasa   Image optimacasa
                     
  Terraces of first and second floor are prepared for the sealing. Bumps are removed, everything sweeped and three layers of the rubber compound are used to seal the terraces.

The effluents are blocked and on Thursday evening we begin with filling up the terraces. Almost up to the foot barrier we fill and leave the water there until Monday morning to be sure it is water-proof.
Image optimacasa
                     
  Image optimacasa Image optimacasa
                     
  Image optimacasa Image optimacasa
                     
  Image optimacasa   Image optimacasa
                     
March 15, 2010 The second big delivery of Mares stones and treads has arrived. Everything was sorted and decked
in the right direction.
  Image optimacasa
                     
March 12, 2010 Until the end of the week, he biggest part of the ceiling on ground floor is ready, as well as the floors in the basement are tiled.   Image optimacasa
                     
  Image optimacasa Image optimacasa
                     
  image optimacasa Image optimacasa
                     
March 11, 2010 The whole week we work on the ceilings. First floor is ready now and the "Esquineros", the edge reinforces are set and plastered.   Image optimacasa
                     
  Image optimacasa Image optimacasa
                     
  Image optimacasa   Image optimacasa   Image optimacasa
                     
  The fundaments of the pool and the side walls are prepared. Of course it has become very muddy with all the rain of this week. This reminds us of the works on the basement last year. Image optimacasa
                     
March 9, 2010 As soon as the weather is better, we will finish the works on the roof. The chimney tops have to be set and the side walls still wait for their final rendering.

  Image optimacasa
                     
March 6, 2010 I promised it, and so I do it now. It is cold and windy in 10 mts height but until Friday noon, the mares stones of the window frames and the roof overhang is painted with a seal of impregnated. Image optimacasa
March 5, 2010 The machinery room slowly gets its machines and the first works at the electrical steering start. Jens is continuing the pipeworks for the different components. Image optimacasa
Image optimacasa
After testing the water profeness, now the roof terrace can be tiled. In the centre we will insert a relaxing seam, because up here there will be high temperature variation.

Also the basement room in the back is ready tiled until the end of the week.
Image optimacasa
March 4, 2010 Image optimacasa Image optimacasa
Image optimacasa Image optimacasa
Until the window frames within the house are prepared further, we already begin with the final casting works at the ceiling.

The rougly cast ceilings are finished and get a fine coat.

The now even ceiling has a stucco texture.

Image optimacasa Image optimacasa
  Image optimacasa   Image optimacasa
Image optimacasa Image optimacasa
The area in front of the basement wall and the rooms of the pool technics was excavated by the caterpillar and now the wall will be cast, sealed with tar and a drainage foil. Image optimacasa
Image optimacasa Image optimacasa
March 2, 2010 We proofed the work! On Monday we had the Balearic Holiday and there were no works going on. Therefore the roof terrace had full three days to show that it is waterproof.

The drains have been blocked last Friday and we filled 15 cm water on the terrace. Until Tuesday, no drop of water came through the roof.
Image optimacasa